Update: Pay and Employment Equity Reviews in the Tertiary Sector No.6
31 March 2009
News
Almost there!
Five ITPs (Otago, Telford, Waiāriki, NMIT and UCOL) and Te Wānanga o Aotearoa plan to have their review reports and action plans finalised by the end of April.
Contents
- News!
- University update
- Wānanga update
- Update from ITPs
- Project managers’ corner
- Key dates
University update
Massey University has started the pay and employment review journey! Discussions are underway to establish the university sub-sector group.
Wānanga update
Te Wānanga o Aotearoa (TWOA) is currently completing their issue identification and action planning. They will complete their review report and action plan by 30 April.
Update from ITPs undertaking a PaEE review
Janice Burns (acting for Rae Torrie) contacted all the project managers for the ITPs to get an update on progress. Five ITPs will complete their reviews by the end of April, and the other institutions that started last year will complete in May or June. The ITPs that started the review early this year are due to complete their reviews by August.
Below is a summary of progress to date.
ITP |
Progress |
| Aoraki Polytechnic | Examining issues Finished May-June |
| Bay of Plenty Polytechnic | Ironing out PEEAT issues Finish date end June |
| Christchurch Polytechnic Institute of Technology | Committee training complete Sorting out data for running PEEAT Finish date end August |
| Eastern Institute of Technology | Are identifying the issues Finish date April-May |
| Nelson Marlborough Institute of Technology | Finishing the final report Finish date end April |
| Northland Polytechnic | Survey about to go out Committee training complete Finish date end August |
| Otago Polytechnic | Report being finalised Finish date end of April |
| Tai Poutini Polytechnic | Have completed gender profile Finish date end May |
| Telford Rural Polytechnic | Finishing completing the gender profile Identifying issues Finish date end April |
| The Open Polytechnic of New Zealand | Survey ‘out’ Ironing out PEEAT issues Committee training complete Finish date end August |
| UNITEC | Survey being piloted Committee training complete |
| Universal College of Learning | Doing a final examination of the issues Following up with part time staff on their particular issues Finish date end April |
| Waikato Institute of Technology | Survey out and PEEAT data coming on stream Committee training complete Finish date end August |
| Waiāriki Polytechnic | Working through last of PEEAT material Finish date end April |
| Whitireia Community Polytechnic | Planning the project set up. |
Project managers’ corner
Identifying issues for part- time staff
The UCOL project manager gave a good example of some further exploratory work they are doing in response to one of their survey findings. They have a large number of part time staff and felt they needed to understand the experiences of these staff better. They have sent an email survey, with just four to five question, by way of follow up to all part-time staff. One of the questions asks why people are working part-time and another inquires about their access to project work (as a career enhancing opportunity).
Occupational segregation
The issue of an equity analysis of female-dominated occupations came up again in discussion. Janice referred the project managers to the information in UPEERTS 5.
Reporting findings to staff
An issue raised by one of the project managers was the best process for reporting findings to staff and seeking ideas on addressing the issues. Keeping staff connected to the process is important. They will inevitably be part of any changes the organisation is suggesting and need to feel there is some relationship between their input and the committee’s decisions. Remember, even if their feedback, “does not change your findings, it may influence the way the organisation needs to respond” (p. 20 of the Workbook).
Suggestions for how to seek feedback can be found in Step 3 of the Workbook (pp. 20-21). One of the simplest ways, and one that has been effective in a number of places, is to send a personal email to staff outlining the issues and inviting their suggestions. However, the process of getting information to staff and inviting feedback will vary between organisations, partly depending on your ‘culture’ of communication. In the teleconference discussion the project managers agreed that it is important to time this communication when the committee is confident about the issues they have identified and prioritised.
Sector-wide issues
As project managers many of you will now be working with your committees on responses to identified gender issues. It is important to keep an eye out for factors that contribute to gender inequities that may not be within the power of the organisation to change but which may have some sector-wide implications. Examples of these factors may be the labour market, collective agreements, or funding – and there may be others we have not yet thought of! Keep your eyes open for these and do report on them.
General
Remember to send your completed gender profile to Rae (those who haven’t already done so!). She is willing to provide feedback to assist your gender analysis. Those institutions which have previously received some gender analysis feedback on their data have reported that they found it useful to feed into their committee discussions.
Rae will be making regular phone contact with the project managers.
Teleconference
Six project managers joined Janice Burns on the teleconference on 18th March. There was a mixture of ‘old hands’ and new project managers. While facing different current issues, it was useful for new people to hear others reflect on some of their experiences (e.g. on issues for part time workers, occupational segregation, working with PEEAT, and reporting project findings to staff) during the course of their reviews.
One reminder was the importance of keeping minutes of the committee’s discussions. This should not be a verbatim recording but rather a ‘logic trail’ of decisions and the rationales for those decisions – especially around deliberations of ‘explainable and justifiable’ and the issues that are selected as priority for the organisation. These minutes will be invaluable when writing the final review report.
The next teleconference will be on April 1st from 10-11.30 with Rae Torrie. We would urge the new project managers to diary this fortnightly opportunity for discussion and feedback.
Key dates
- Wednesday 1 April Project managers’ teleconference
- Wednesday 29 April ITP sub-sector meeting
- Tuesday 5 May TST Steering Group meeting.





















